- 09-09-24Periodic maintenance power distribution BIT-2BCD
- 14-08-24Maintenance fire suppression BIT-2BCD
- 01-08-24Periodic maintenance fire detection and suppression system BIT-1
- 17-07-24Moving core network equipment in BIT-1
- 16-07-24Moving core network equipment in BIT-1
- 03-07-24Maintenance Microsoft SQL instances servers
- 02-07-24Fiber maintenance BIT-2 - Interxion Science Park (AMS9)
- 28-06-24Maintenance power generators BIT-2A
- 11-06-24Black building emergency power test BIT-2
- 11-06-24Maintenance management software virtualisation platform
Periodic maintenance power distribution BIT-2BCD
09-09-2024 00:00:00
- 12-09-2024 06:00:00
Urgency: Planned
Affected services:
- Feed A and B BIT-2B
- Feed A and B BIT-2C
- Feed A and B BIT-2D
Expected Impact: No
Customer intervention required: No
Reference number: 193100
Summary:
Periodic maintenance will be performed on the power distribution of BIT-2BCD.
Details:
From September 9, 2024, to September 12, 2024, between 00:00 and 06:00, periodic maintenance and a thermographic inspection will be carried out on the power distribution of BIT-2BCD. During this maintenance, all switches of the BIT-2BCD power distribution will be serviced. The UPS systems will be placed in bypass mode one by one for this purpose.
If the feed from the respective UPS system is interrupted during this maintenance, which we do not expect, the other feed will be available as normal. We strongly advise checking if all your equipment is connected to both feeds.
The entire maintenance will be supervised by BIT's datacenter engineers.
Affected services:
- Feed A and B BIT-2B
- Feed A and B BIT-2C
- Feed A and B BIT-2D
Expected Impact: No
Customer intervention required: No
Reference number: 193100
Summary:
Periodic maintenance will be performed on the power distribution of BIT-2BCD.
Details:
From September 9, 2024, to September 12, 2024, between 00:00 and 06:00, periodic maintenance and a thermographic inspection will be carried out on the power distribution of BIT-2BCD. During this maintenance, all switches of the BIT-2BCD power distribution will be serviced. The UPS systems will be placed in bypass mode one by one for this purpose.
If the feed from the respective UPS system is interrupted during this maintenance, which we do not expect, the other feed will be available as normal. We strongly advise checking if all your equipment is connected to both feeds.
The entire maintenance will be supervised by BIT's datacenter engineers.