- 21-11-24Een goede cloud heeft een kundige dirigent nodig
- 17-10-24ECOFED wint ICT Innovatieprijs Regio Foodvalley 2024
- 01-08-24BIT geeft kaarten weg voor F1 in Zandvoort
- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
Periodic maintenance cooling system BIT-2BCD
14-10-2024 08:00:00
- 29-10-2024 17:30:00
Urgency: Planned
Affected services:
- Colocation in BIT-2BCD
Expected impact: Slight increase in temperature
Customer intervention required: No
Reference number: 194115
Summary:
Periodic maintenance is performed on chillers and downflow units in BIT-2BCD.
Details:
The downflow units (responsible for blowing cold air in the data centers) will be shut down for maintenance one at a time. This may result in a slight temporary increase in temperature in specific parts of the data center.
The chillers of BIT-2BCD will be shut down for maintenance one at a time as well. The remaining three chillers have sufficient capacity to cool the data center.
The maintenance will take place every workday between 08:00 and 17:30 hrs
This maintenance will be supervised by BIT engineers who will monitor the temperature in the data center closely.
Affected services:
- Colocation in BIT-2BCD
Expected impact: Slight increase in temperature
Customer intervention required: No
Reference number: 194115
Summary:
Periodic maintenance is performed on chillers and downflow units in BIT-2BCD.
Details:
The downflow units (responsible for blowing cold air in the data centers) will be shut down for maintenance one at a time. This may result in a slight temporary increase in temperature in specific parts of the data center.
The chillers of BIT-2BCD will be shut down for maintenance one at a time as well. The remaining three chillers have sufficient capacity to cool the data center.
The maintenance will take place every workday between 08:00 and 17:30 hrs
This maintenance will be supervised by BIT engineers who will monitor the temperature in the data center closely.