- 01-04-25BIT as a Service
- 26-03-25Internetproviders verliezen rechtszaak over blokkeren websites
- 19-02-25BIT introduceert server-side e-mailfiltering met Sieve
- 06-02-25Shared hosting wordt opgefrist
- 28-11-24ECOFED uitgeroepen tot publieksfavoriet bij Computable Awards
- 21-11-24Een goede cloud heeft een kundige dirigent nodig
- 17-10-24ECOFED wint ICT Innovatieprijs Regio Foodvalley 2024
- 01-08-24BIT geeft kaarten weg voor F1 in Zandvoort
- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
Maintenance UPS BIT-2D B-Feed
14-10-2024 07:00:00
- 16-10-2024 17:30:00
Urgency: Planned
Affected services: Equipment in BIT-2D
Expected impact: Geen
Customer intervention required: No
Reference number: 188041
Summary:
From Monday 14 October to Wednesday 16 October, our supplier will perform maintenance on the UPS (B-Feed) in BIT-2D between 07:00 and 17:30. During the maintenance, the batteries of the B-feed will be replaced.
Details:
During the maintenance, 25% of the batteries will be disconnected at a time. The UPS set are designed in a modular way, so 75% of the battery capacity for each feed will still be available. This capacity is sufficient to handle a power outage from the grid for approximately 20 minutes.
In the unlikely event that the feed of a particular UPS set is interrupted during the maintenance, the other feed will remain operational. We strongly advise you to double-check if all your equipment is connected to both feeds.
Affected services: Equipment in BIT-2D
Expected impact: Geen
Customer intervention required: No
Reference number: 188041
Summary:
From Monday 14 October to Wednesday 16 October, our supplier will perform maintenance on the UPS (B-Feed) in BIT-2D between 07:00 and 17:30. During the maintenance, the batteries of the B-feed will be replaced.
Details:
During the maintenance, 25% of the batteries will be disconnected at a time. The UPS set are designed in a modular way, so 75% of the battery capacity for each feed will still be available. This capacity is sufficient to handle a power outage from the grid for approximately 20 minutes.
In the unlikely event that the feed of a particular UPS set is interrupted during the maintenance, the other feed will remain operational. We strongly advise you to double-check if all your equipment is connected to both feeds.