- 28-11-24ECOFED uitgeroepen tot publieksfavoriet bij Computable Awards
- 21-11-24Een goede cloud heeft een kundige dirigent nodig
- 17-10-24ECOFED wint ICT Innovatieprijs Regio Foodvalley 2024
- 01-08-24BIT geeft kaarten weg voor F1 in Zandvoort
- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
Black building emergency power test BIT-2
10-12-2024 05:00:00
- 10-12-2024 07:00:00
Urgency: Planned
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 194898
Summary:
On Tuesday, December 10th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Update placed at 11/12/2024, 14:42
This maintenance was completed succesfully at 6:22 hrs. If you have any questions regarding this maintenance, please contact the Customer Care department by phone on +31 (0)318 648 688 or by email on support@bit.nl.
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 194898
Summary:
On Tuesday, December 10th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Update placed at 11/12/2024, 14:42
This maintenance was completed succesfully at 6:22 hrs. If you have any questions regarding this maintenance, please contact the Customer Care department by phone on +31 (0)318 648 688 or by email on support@bit.nl.