- 05-02-25Periodic maintenance fire detection and suppression system BIT-1
- 13-01-25Periodic maintenance power generators BIT-2A
- 13-01-25Periodic maintenance power generators BIT-2BCD
- 13-01-25Periodic maintenance power generator BIT-1
- 09-01-25Maintenance management software virtualisation platform
- 02-01-25Adaptation temperature datacenter BIT-1/BIT-2ABCD
- 20-12-24Periodic maintenance on all cooling pumps of BIT-2
- 20-12-24Periodic maintenance fire suppression BIT-2ABCD
- 20-12-24Periodic maintenance fire suppression BIT-1
- 19-12-24Maintenance shared MySQL databases
Black building emergency power test BIT-2
10-12-2024 05:00:00
- 10-12-2024 07:00:00
Urgency: Planned
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 194898
Summary:
On Tuesday, December 10th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Update placed at 11/12/2024, 14:42
This maintenance was completed succesfully at 6:22 hrs. If you have any questions regarding this maintenance, please contact the Customer Care department by phone on +31 (0)318 648 688 or by email on support@bit.nl.
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 194898
Summary:
On Tuesday, December 10th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Update placed at 11/12/2024, 14:42
This maintenance was completed succesfully at 6:22 hrs. If you have any questions regarding this maintenance, please contact the Customer Care department by phone on +31 (0)318 648 688 or by email on support@bit.nl.