- 19-02-25Maintenance building management system
- 12-02-25Maintenance core routers BIT-1 and BIT-2A
- 05-02-25Periodic maintenance fire detection and suppression system BIT-1
- 04-02-25Maintenance various services
- 13-01-25Periodic maintenance power generators BIT-2A
- 13-01-25Periodic maintenance power generators BIT-2BCD
- 13-01-25Periodic maintenance power generator BIT-1
- 09-01-25Maintenance management software virtualisation platform
- 02-01-25Adaptation temperature datacenter BIT-1/BIT-2ABCD
- 20-12-24Periodic maintenance on all cooling pumps of BIT-2
Maintenance building management system
19-02-2025 07:00:00
- 11-04-2025 17:30:00
Subject: Replacement building management system BIT-2ABCD
Urgency: Planned
Time window:
- 19/02/2025 07:00 - 11/04/2025 17:30 hrs
Affected services:
- Colocation in BIT-2ABCD
Expected impact: Slight increase or decrease in temperature
Customer intervention required: No
Reference number: 185383
Summary:
The building management system at BIT-2ABCD will be replaced
Details:
The controllers of the building management system in all control cabinets of BIT-2 will be replaced one by one. This will be done in phases and will start on February 19, with a planned end date of April 11.
BIT datacenter engineers will supervise the maintenance and also monitor the temperature in BIT-2ABCD during the maintenance.
Urgency: Planned
Time window:
- 19/02/2025 07:00 - 11/04/2025 17:30 hrs
Affected services:
- Colocation in BIT-2ABCD
Expected impact: Slight increase or decrease in temperature
Customer intervention required: No
Reference number: 185383
Summary:
The building management system at BIT-2ABCD will be replaced
Details:
The controllers of the building management system in all control cabinets of BIT-2 will be replaced one by one. This will be done in phases and will start on February 19, with a planned end date of April 11.
BIT datacenter engineers will supervise the maintenance and also monitor the temperature in BIT-2ABCD during the maintenance.