Maintenance UPS-sets BIT-2A feed B

Maintenance UPS-sets BIT-2A feed B

10-08-2015 05:00:00 - 14-08-2015 17:30:00

From Monday, August 10th until Friday, August 14th between 5.30h and 17.30h our UPS supplier will perform maintenance on the UPS'es of the B-feed of BIT-2A. 

During this maintenance the UPS'es of the B-feed will be replaced with four new models. This replacement will be done two by two, so at all times two UPS'es of the B-feed will remain available.

We do not expect any disruption in the power supply. If you have received warnings from BIT that your total power consumption is close to the limit, we recommend that you take action before this maintenance starts.

In case of disruption of one of the power feeds, which we do not expect,  the other feed will be available as normal. We do recommend that you check if your equipment is connected to both power feeds.

During the maintenance it is possible to see a slight increase of temperature. This is due to the fact that we need to disassemble a part of the cold corridor to move the UPS'es. After the UPS replacement the cold corridor will be rebuilt.

If you have any questions regarding this maintenance, please contact the Customer Care department by phone on +31 (0)318 648 688 or by email on support@bit.nl